We will be adding additional videos this week of the progress being made clearing the debris from the Ada Drift.
Currently, the team is approximately 6-8 feet from the North Tunnel. The North Tunnel is what was worked previously by Thomas and the team and were we will begin extracting raw ore. We are currently waiting for the steel reinforcements to be delivered. Once it is delivered we will add the additional supports needed to continue clearing the rest of the drift and getting back into the North Tunnel.
The fires around the area have been mostly contained and Thomas and the team are expecting to relocate back to the mine site this week.